Morrison School Facility Projects Announced

Posted by

Superintendent DeBeane presented the proposed facility updates that will be forth coming this summer. The construction projects will consume massive upgrades in all school facilities and summer entrance by non-construction personnel will not be allowed. The following updates will begin upon the end of the normal school year and completed in time for the 2026-2027 school year to begin in September.
The upgrades will total over $8,546,000 and the funding will be utilizing funds from the Health Life Safety Fund, sales tax revenue and bonds.

The following projects will be completed this summer and a special open house will be offered prior to the opening of the 2026-2027 school year to allow the community an opportunity to view the improvements.

The proposed upgrades are as follows:

MORRISON HIGH SCHOOL:

  • Replacing ceiling and LED lighting on the lower level, 1st. floor and 2nd floor
  • Replacing flooring in the main corridors on the 1st and 2nd floors
  • Replace the pool locker room and kitchen domestic water heaters and storage tanks
  • Upgrading the electrical distribute panels and panelboards
  • Adding additional electrical receptacles n several classrooms
  • Installing additional LED lighting, safety platforms, ladders, and railings in the mechanical rooms
  • Replacing existing wood supports and roof-mounted natural gas piping with new supports
  • Replacing the auditorium curtains and rigging
  • Upgrading the gymnasium, which incudes a new acoustical ceiling, upgraded LED lighting, refinishing the hardwood flooring, repairing masonry, and adding a center screen divider, and digital clocks
  • Expanding the rear parking lot from 185 to 210 stalls and renovating the driveway paving

 

MORRISON JUNIOR HIGH SCHOOL:

  • Replace three domestic water heaters and recirculating pumps
  • Replace wood supports for roof-mounted natural gas piping with engineered supports
  • Replacing windows in the 1959 section with new tinted insulated windows and aluminum frames
  • Installing safety railings and ladders in the mezzanines
  • Replacing three sets of exterior double doors with a new storefront system
  • Improving site drainage by adding underground piping for downspouts

SOUTHSIDE ELEMENTARY

  • Replacing two domestic water heaters
  • Installing new flooring in classrooms, offices, gymnasium and cafeteria
  • Renovating restrooms to be ADA compliant. Including new ceilings, lights, plumbing fixtures, partitions, epoxy floors, and roof-mounted exhaust fans
  • Adding exterior LED lighting wall packs on the front of the building for safety
  • Improving site drainage by installing underground pipping for downspouts

NORTHSIDE ELEMENTARY SCHOOL:

  • Replacing three domestic water heaters
  • Renovating restrooms with new ceiling, lighting, partitions, ADA plumbing fixtures, epoxy flooring and exhaust fans
  • Adding new LED wall packs to the door for the Music Classroom/Storage Area
  • Installing new flooring and wall base in the South classrooms
  • Replacing original building windows and door to the playground