May3DonnybrookCorner

Main Street Renovation Began May 3

Posted by

Assistant Editor Jerry Lindsey will document construction each week.  These were taken on Week 1, Day 1.

On Monday, May 3, 2021, the Morrison, IL, Main Street Renovation commenced.  Willett Hofmann & Associates, Inc., Sterling, IL, will manage this major transformation of the downtown:  below the street; at street level; atop sidewalks.  City Administrator Barry Dykhuizen will update citizens of each week’s planned work for Monday to Friday.

Construction Activity
● Construction of water main on Main Street from Orange Street to Base Street.
● Existing pavement, sidewalk, curb, and gutter will be removed on Orange Street, from Market Street to U. S. Route 30.

Street Closures
● Orange Street:   Market Street to U. S. Route 30 will be closed to traffic.
● Main Street:  Orange Street to Base Street will be closed to traffic from approximately 6:00 a.m. to 5:00 p.m.