Main Street Construction Activity June 21 to June 25

Posted by

The Editor took the photo at U. S. Route 30 and Orange Street.

Below is Main Street Redevelopment Project Update #8.

OrangeSidewalksJune18sConstruction Activity, June 21-June 25

  • Pour concrete pavement on Orange Street.
  • Remove sidewalk, curb and gutter, pavement and driveways on Main Street from Base Street to Genesee Street and on Base Street.
  • Install watermain on Main Street from Genesee Street to Cherry Street.

 

 

 

 

 

Work Completed June 14 – 18

  • Concrete pavement was installed on Market Street east of Orange Street and on Main Street west of Orange Street.
  • ADA ramps on the west side of Orange Street at Main Street were poured.
  • The island for the Post Office was poured.
  • Sidewalk on Orange Street was completed.
  • Insertion valves were installed and the existing watermain was lowered, at Main Street and Base Street.
  • Storm sewer was completed at Base Street and Main Street and Base Street and Market Street.

Street Closures

  • Orange Street, from Market Street to U. S. Route 30, will be closed.
  • Main Street from Orange Street to Genesee Street will be closed.
  • Base Street from U. S. Route 30 to Market Street will be closed.
  • Main Street from Genesee Street to Cherry Street will be closed from 7:00 a.m. to 5:30 p.m., when the contractor is working on the watermain.