Below is Main Street Redevelopment Project Update #8.
Construction Activity, June 21-June 25
- Pour concrete pavement on Orange Street.
- Remove sidewalk, curb and gutter, pavement and driveways on Main Street from Base Street to Genesee Street and on Base Street.
- Install watermain on Main Street from Genesee Street to Cherry Street.
Work Completed June 14 – 18
- Concrete pavement was installed on Market Street east of Orange Street and on Main Street west of Orange Street.
- ADA ramps on the west side of Orange Street at Main Street were poured.
- The island for the Post Office was poured.
- Sidewalk on Orange Street was completed.
- Insertion valves were installed and the existing watermain was lowered, at Main Street and Base Street.
- Storm sewer was completed at Base Street and Main Street and Base Street and Market Street.
Street Closures
- Orange Street, from Market Street to U. S. Route 30, will be closed.
- Main Street from Orange Street to Genesee Street will be closed.
- Base Street from U. S. Route 30 to Market Street will be closed.
- Main Street from Genesee Street to Cherry Street will be closed from 7:00 a.m. to 5:30 p.m., when the contractor is working on the watermain.